Location - The City, London
Project Duration - 6 Weeks
Project Costs - £ 53,000.00

ITOPF

The City, London

An office reconfiguration project to maximise space within current floor to allow for future expanision and complete decoration as per tenancy requirements.

Project was completed over 6 week period predominantly during office hours working alongside the client to ensure minimum disruption to staff.

Project included relocation of server room including installation of new cabling to all services through-out the office to existing and new floor boxes, relocation of existing air conditioing unit and installation of new flooring. This element of the project was undertaken over one weekend to ensure there was no disruption to services during office hours.

Project Wren

Project Elements

  • Installation of new glazed full height partition
  • Relocation of library and furniture
  • New lighting within library area
  • New carpet throughout main office
  • Full decoration
  • Server room relocation
  • Relocation of existing services to suit new desk layout
  • Redesign of kitchen area

Project Reference

''We engaged STP Solutions as contractors for our office refit project back in September this year. The project value was approximately £50K. The actual works lasted for 6 weeks.

Considering we took the decision to have this work carried whilst still occupying the office space, it was at times difficult, but STP were always on hand to help us as and when needed.

The project was carried out with the upmost professionalism by these contractors and all their personnel.

I would not hesitate to recommend STP Solutions in the future.''

Administration & Personnel Assistant,
ITOPF